Following the successful completion of the double surface dressing along the Independence Stadium Road section, the contractor has now commenced the laying of interlocking pavement blocks in the Senegambia area on both sides of the road.

In addition, sand stabilisation works are currently ongoing around Marouns Supermarket, covering the right sides of the service road.
Meanwhile, the contractor is also carrying out scaffolding works for the bridge deck at the Sukuta–Jabang Overpass. At the same time, hexagonal concrete panels for the embankment protection of the overpass are being cast at the Arezki construction camp located behind the Airport.

The works form part of the broader effort to enhance the Bertil Harding Highway corridor and improve traffic flow along one of the country’s busiest transport routes.